October 2018

  • Roofing project 98% complete
  • Secure lobby submitted for permit

At Our School

Total Estimated Project Cost: $3.9 million

Safety improvements

A new secure lobby will be constructed. A second crosswalk will be added at 27th Street and keys for the school will be standardized. ADA improvements will also take place.

Maintenance and preservation

New roofs will be installed on buildings A, B, C and the wood shop.

Energy conservation

HVAC system will be updated.

Technology

New technology includes installing ceiling projector mounts, installing key card access for all exterior access doors, modernizing HVAC controls and modernizing wireless wiring.

Modernize classrooms

Athletic areas will have climate regulation.