October 2018: Moving into design development.
May 2018: BBT Architects has been selected and the project is in the programming phase to identify the scope of the work. Schematic design is slated to be complete by the start of summer.
Total Estimated Project Cost: $6.2 million
The bond will fund the addition of a new multi-use instructional space and a kitchen. Ceiling fans will also be installed to regulate classroom climate.
A new secure lobby will be constructed.
Roofs will be replaced on Buildings A, B and C; duct-work will be upgraded; the drainage between Buildings B and C will be improved.
All single pane windows will be replaced and HVAC controls will be modernized.
New
technology includes installing ceiling
projector mounts, installing key card access for exterior doors, and modernizing wireless wiring.
1300 NE Norton Ave
Bend, OR 97701
Opened 1965